package common
|
|
|
|
const (
|
|
// 工单状态
|
|
WO_STATUS_UNPLANNED = 10 // 未计划
|
|
WO_STATUS_PLANNED = 20 // 已计划
|
|
WO_STATUS_LOCKED = 24 // 已锁定
|
|
WO_STATUS_RELEASED = 26 // 已下达,生成序列订单
|
|
WO_STATUS_INTERRUPT = 39 // 中断中
|
|
WO_STATUS_RUNNING = 40 // 生产中
|
|
WO_STATUS_FINISHED = 80 // 已完成
|
|
WO_STATUS_FROZEN = 95 // 冻结
|
|
WO_STATUS_CANCELED = 98 // 取消
|
|
|
|
RES_STATUS_AVAIL = 1 // 资源状态可用
|
|
RES_STATUS_UNAVAIL = 0 // 资源状态不可用
|
|
OP_UNSCHEDULED = 0 // 未调度
|
|
OP_SCHEDULED = 1 // 工序在内存中的调度状态:已调度
|
|
|
|
// 计划资源负载类型
|
|
WORKLOAD_TYPE_MONTHLY = "MONTHLY"
|
|
WORKLOAD_TYPE_WEEKLY = "WEEKLY"
|
|
WORKLOAD_TYPE_DAILY = "DAILY"
|
|
WORKLOAD_TYPE_SHIFT = "SHIFT"
|
|
WORKLOAD_TYPE_HOURLY = "HOURLY"
|
|
|
|
// 时间类型
|
|
TIME_UOM_WEEK = "WEEK"
|
|
TIME_UOM_DAY = "DAY"
|
|
TIME_UOM_HOUR = "HOUR"
|
|
TIME_UOM_MINUTE = "MINUTE"
|
|
TIME_UOM_SECOND = "SECOND"
|
|
|
|
// 物料需求变化类型
|
|
ART_CHANGE_PURCHASE = 1 // 物料采购到货
|
|
ART_CHANGE_CONSUME = 2 // 物料消耗
|
|
ART_CHANGE_PRODUCE = 3 // 物料产出
|
|
|
|
// 工序资源需求时段
|
|
OP_DEMAND_SETUP = "SETUP" // 换型时段
|
|
OP_DEMAND_PROD = "PROD" // 计划生产时段
|
|
OP_DEMAND_AFTERPROCESS = "AFTERPROCESS" // 后处理时段
|
|
|
|
// 表时间字段更新模式
|
|
MODIFY_MODE_CREATE = "CREATE"
|
|
MODIFY_MODE_UPDATE = "UPDATE"
|
|
MODIFY_MODE_DELETE = "DELETE"
|
|
|
|
// 前后工序的关联关系
|
|
OP_RELATION_ES = "ES" // End-Start 前工序结束,本工序才能开始
|
|
OP_RELATION_SS = "SS" // Start-Start 前工序开始,本工序即可开始
|
|
OP_RELATION_SSEE = "SSEE" // Start-Start End-End 前工序开始本工序开始,前工序结束本工序结束(类似于块的概念)
|
|
OP_RELATION_EES = "EES" // End-Each-Start 前工序开始与本工序之间的关系,取决于转运批量
|
|
OP_RELATION_ESE = "ESE" // End-Start-Each 前工序结束与本工序之间的关系,取决于转运批量
|
|
|
|
)
|